The following table represents a hypothetical situation where the differences in
NPV, B/C ratio and IRR are presented. In this situation it may be best to choose project B because it is ranked first in NPV and
IRR, even though it does not have the best B/C ratio. However, this is subjective comment and perhaps project C should be chosen because it has a greater return per dollar invested (i.e. B/C ratio).
Project
NPV |
B/C
ratio |
IRR |
A |
$10,000 |
2:1 |
18% |
B |
$11,000 |
3:1 |
19% |
C |
$9,000 |
5:1 |
17% |
Note: It is important that the risk aspects are
also taken into account, using some form of sensitivity analysis, to assess the
risks of failure to find, import and release agents to successfully control the
target pest.
[ Back ] [ Next ]
David Adamson